Binh Duong Province hands over construction site for Tan Uyen 500kV work cluster in August

On 19 July, 2018, Deputy Chairman of Binh Duong Provincial People's Committee (PPC) Mai Hung Dung chaired the meeting with relevant departments, branches and the Southern Vietnam Power Projects Management Board (SPMB) to solve difficulties, problems in compensating for site clearance of works: the 500kV Song May - Tan Uyen line, Tan Uyen 500kV substation and connection.

Leaders of Binh Duong PPC working with departments, branches and SPMB to provide solutions to handle obstacles for 500kV work cluster in Binh Duong Province.

Mr. Doan Tan Phong - Director of SPMB said: the section included in 500kV Song May - Tan Uyen line is run through Binh Duong province in a length of 1.66 km with 5 posts. Currently, one site location has not been handed over because 4 households here have not received compensation at the regulated unit prices.

For Tan Uyen 500kV substation and its connection, the obstacle is due to 11 households having not received compensation with the total area, not acquired, of over 20,000m2.

SPMB has repeatedly coordinated with the local authorities to mobilize, explain and resolve these households’ proposals but the consensus has not been reached.

Mr. Mai Hung Dung - Deputy Chairman of Binh Duong PPC directed the departments, branches and local authorities to drastically to accelerate the progress and give maximum support for the Investor in constructing national key projects.

Accordingly, the relevant units should urgently complete the prescribed procedures, in cases of need, administrative measures shall be applied if the households fail to comply with the regulations so as to promptly hand over the site to the construction unit in August 2018.


  • 19/07/2018 03:26
  • evn.com.vn
  • 578