Commencement of the installation project of the second transformer in 220kV Thanh My substation

In the afternoon of December 26, 2016, at 220kV Thanh My substation (Thanh My town, Nam Giang district, Quang Nam province), Power Transmission Company No.2 (PTC2) started the Project of upgrading installation capacity of 220kV – 125MVA transformer (second one), expanding 220kV feeder and synchronized equipment.

The project has been designed by Power Engineering Consulting Company No.4;  its design has been then appraised by Power Engineering Consulting Company No.3;  supervision consultancy services will be implemented by EVN International JSC.,; the project will be implemented by Repair-Experiment Team and commissioned and operated by Quang Nam transmission company.

The total investment of the project is VND 25,147 billion, including the following components: installing additional 220/110 kV-125 MVA transformer; adding switchgears for two 220kV and 110kV feeders of the newly installed transformer; adding boundary measuring system for the 110kV feeder of the transformer for measurements; completing the control, protection, scada system in synchronization with the new equipment.

As scheduled, the project shall be be completed for being energized and put into operation by the third quarter of 2017.


  • 26/12/2016 05:39
  • evn.com.vn
  • 1190