Early completion of 220kV Hoa Khanh substation upgrading project

After nearly one month, on December 28, 2016, Power Transmission Company No.2 (PTC2) completed the Project of upgrading capacity of 110 kV – 25 MVA transformer with 110 kV – 63 MVA transformer and synchronous equipment of 220kV Hoa Khanh substation.

According to Mr. Nguyen Tien Dung – Deputy Director of PTC2, the total investment cost of the project is VND 44,105 billion.

The project was designed by the Power Engineering Consulting Constructing Company No. 5; the project design then was appraised by Power Engineering Company No.2; the project was implemented by the Repairing – Experimenting Team under the supervision of EVN International JSC., and commissioned and is now operated by Da Nang Transmission Company.

Putting the project into operation earlier than the planned schedule has contributed to the constant and safe power supply to the loads in Da Nang city and in the region, particularly helping secure power supply during “APEC Economic Leaders' Week (AELW)” under Asia-Pacific Economic Cooperation (APEC) Summit 2017 to be organized in Da Nang.


  • 29/12/2016 03:04
  • evn.com.vn
  • 895