Projects of Underground power lines in Ho Chi Minh City to be implemented

Despite being pro-longed in procedures of routing agreement, design examination, construction permit and other difficulties, the Ho Chi Minh City Power Corporation (EVNHCMC) has confirmed that 60 projects of underground power lines in 62 streets all over the city would be completed in 2016 with good quality assurance.

The implementation of the underground cable projects in Ho Chi Minh city will contribute to improving urban landscape and enhancing quality and stability of the power grid to serve people’s lives.

EVNHCMC is striving to complete the renovation and implementation of the underground power lines in the main uptown streets, inter-district roads and especially complete the underground power lines in all officially-named streets in the center of District 1 and District 3 by the year 2020.

 

 

2011-2015

2016-2020

Total  investment

(VND billion)

2,050

4,200

Length of lines

262 km of medium voltage line, 428 km of low voltage line

650 km of medium voltage lines, 1,150 km of low voltage lines

 

 

 

Quantity of underground cable lines implemented by EVNHCMC:

Year 2016:

- 60 projects, of which 10 projects implemented in synchronization with the key transport projects in the city.
- Total length: 287 km of medium voltage lines, 489 km of low voltage lines;
- Areas: from District 1 to District 6, District10, District 11, Phu Nhuan, Binh Thanh, Tan Binh, Tan Phu, and Go Vap districts.

 