17:56, 13/08/2026
At 11:10 a.m. on August 13, 2026, Unit 1 of the Quang Trach 1 Thermal Power Plant Project successfully reached 100% of its rated load, with an actual output of 701.5MW. The operating parameters of the turbine and boiler remained stable. This marks an important milestone in the commissioning process,...