12:21, 30/01/2026
Amid the increasingly complex power system, rising load demand, and stricter technical requirements, EVN has identified safe operation and reliable...
01:35, 29/01/2026
On January 28, 2026, after inspecting the construction site, EVN Chairman Dang Hoang An chaired a meeting with Power Project Management Board No. 2...
17:06, 27/01/2026
After the accelerated phase at the end of 2025, the Bac Ai pumped storage hydropower Plant project site recorded a series of items that met and...
01:48, 27/01/2026
The People's Committee of Da Nang City issued Decision No. 360/QD-UBND (dated 23 January 2026) approving the investment policy for the Thanh My -...
17:11, 25/01/2026
This is one of the key targets in the 2026 investment and construction plan of the Northern Power Corporation (EVNNPC), aimed at meeting the rapidly...
EVN Partnership Meeting 2026: Building trust, sharing long-term vision for development of Vietnam’s Power Sector
EVN Vice President Ngo Son Hai meets with Israeli Commercial Counsellor in Vietnam
EVN Chairman Dang Hoang An inspects construction site of Bac Ai Pumped Storage Hydropower Plant
Completion of energizing two 500kV shunt reactors at Son La 500kV Substation
Con Dao special zone switches on smart power grid
Nuclear power plant construction considered major strategic project: PM
In 2025, EVN continues to improve power supply reliability and expand digital services
Safe and reliable operation of power sources and grids is continuous requirement in 2026
Bac Ai pumped storage hydropower Plant: Many items ahead of schedule, ready to enter peak construction in 2026