At the location of the VT117 pole (Luc Yen District, Yen Bai Province), under Package No. 3, constructed by Hung An Construction JSC and Viet Vuong JSC, Mr. Dang Hoang An and his delegation conducted an on-site inspection.

At the location of the VT144 pole (Luc Yen District, Yen Bai Province), the contractor has completed the foundation excavation. The EVN Chairman instructed the contractor to take full advantage of the dry weather and urgently proceed with the remaining work.

At the location of the VT210 pole (Yen Binh District, Yen Bai Province), under Package No. 5, implemented by Phuong Hanh Co., Ltd. and Dong Anh Steel Pole Manufacturing Co., Ltd., the Chairman inspected the construction progress. The contractor is expected to complete the reinforced concrete foundation on June 25.

At the location of the VT240 pole (Luc Yen District, Yen Bai Province), the contractor is currently pouring concrete for the third foundation base. The temporary access road to this position is steep and winding, causing many challenges. After each rainstorm, the road has to be reopened and repaired, leading to significant time and labor costs. Currently, taking advantage of dry weather, the contractor has mobilized maximum manpower and vehicles, working overtime to transport materials and equipment to the site. Workers are also stationed on-site full-time to ensure continuous construction operations.