Hoa Binh Hydropower Expansion Project: "Realizing Scheduled Target" of 2024 plan targets

20:12, 26/12/2024

Inspecting the construction site of the Expanded Hoa Binh Hydropower Plant on December 26, EVN’s Vice President Pham Hong Phuong praised the Power Project Management Board No. 1 (EVNPMB1) and contractors and construction forces for their great efforts, basically completing all project progress targets in 2024.


EVN’s Vice President Pham Hong Phuong (second from right) inspecting construction of Hoa Binh Hydropower Plant Expansion Project.

Vice President Pham Hong Phuong requests Power Project Management Board No. 1 and contractor to continue promoting achieved results, implementing construction to ensure progress, quality, safety, and determination to complete project on schedule in 2025.

Group leaders congratulating construction teams on achieving many important milestones in 2024

Construction area of ​​Expanded Hoa Binh Hydropower Plant. In 2024, reinforced concrete project of plant reached 103% of plan.

Basic equipment installation is on schedule, following plant's concreting plan.

At water intake area, reinforced concrete construction item has surpassed annual plan by 28%. This is important premise for project to quickly reach goal of generating 2 units in 2025