EVN’s Vice President Pham Hong Phuong (second from right) inspecting construction of Hoa Binh Hydropower Plant Expansion Project.
Vice President Pham Hong Phuong requests Power Project Management Board No. 1 and contractor to continue promoting achieved results, implementing construction to ensure progress, quality, safety, and determination to complete project on schedule in 2025.
Group leaders congratulating construction teams on achieving many important milestones in 2024
Construction area of Expanded Hoa Binh Hydropower Plant. In 2024, reinforced concrete project of plant reached 103% of plan.
Basic equipment installation is on schedule, following plant's concreting plan.
At water intake area, reinforced concrete construction item has surpassed annual plan by 28%. This is important premise for project to quickly reach goal of generating 2 units in 2025