The cluster of works to release capacity for the Van Phong 1 BOT Thermal Power Plant includes the Van Phong 500kV substation and connection, Van Phong - Vinh Tan 500kV transmission line, 500kV transmission line connecting Thuan Nam 500kV substation to the Van Phong - Vinh Tan 500 kV transmission line.
According to the schedule committed with the investor of Van Phong 1 BOT Thermal Power Plant, this project cluster must be completed before December 26, 2022. The construction time of this project is very short compared to that of other projects of similar size and nature.
Groundbreaking ceremony of Van Phong 500kV substation and connection, September 2021
EVN General Director Tran Dinh Nhan holding an online meeting with leaders of Khanh Hoa and Ninh Thuan provinces on the site clearance and clearance of the project cluster to release capacity for Van Phong 1 BOT thermal power plant, September 2021.
The delegation of EVN leaders, EVNPT checking the construction progress of Van Phong 500kV substation, March 18, 2022 in Khanh Hoa province
The delegation of EVN/EVNNPT presents gifts to the construction force at position 130 of the Van Phong - Vinh Tan 500kV transmission line, on the occasion of the Lunar New Year of the Tiger 2022.
By the end of September 2022, the site clearance work of Van Phong 500kV substation and the 220kV connection line has been basically completed and handed over by the locality. In the construction work, many important items have been completed and it is expected that by the end of October 2022, such items will be basically completed.
For the Van Phong - Vinh Tan 500kV transmission line project, up to now, 304/304 foundation positions have been handed over. In Khanh Hoa province, for part of the corridor, 172/172 column intervals have been handed over; Ninh Thuan province handed over 126/132 column intervals (reaching 95.5%). Regarding the construction volume, the foundation excavations have been performed at all 304/304 foundation positions, 301/304 positions have been finished casting. The column erection has been completed at 270/304 positions, currently erecting columns at 19 positions. The cables with 23/79 anchorages have been pulled, and 16 anchorages are being pulled.
In respect of the progress of the 500kV line connecting the Thuan Nam 500kV substation to the Van Phong - Vinh Tan 500kV transmission line has completed: excavating, casting 3/3 foundation positions, erecting 2/3 column positions, erecting 2/3 column positions, pulling cable 0.841/1.27 km.
EVNNPT General Director – Mr. Pham Le Phu said that the progress of the project is very positive and is on the way to reach the finish line. During the remaining 2 months, the investor will urge the contractor to supply materials and equipment, and carry out the construction of cables and wire on schedule; coordinate with the dispatching levels to arrange a reasonable power outage schedule, coordinate with Van Phong 1 BOT Thermal Power Plant to conduct synchronous connection as trial.
EVNNPT Leaders have also asked construction contractors to absolutely ensure the safety of people and equipment during the construction process. Along with that, it is required to mobilize maximum human resources to meet the requirements. During the construction process, it does not affect the quality of the project because of the progress.