Duyen Hai 3 Extention Thermal Power Plant

1. General

Name of project:

Duyen Hai 3 Extention Thermal Power Plant

Investor :

Vietnam Electricity

Project manager:

Power Generation Corporation 1 / Thermal Power Project Management Board 3

Project location:

Lam Son Commune, Ninh Son District, Ninh Thuan Province

Total investment:

VND 22,774 billion

Investment sources:

International loan (85%); reciprocal capital (15%)

Project scale:

660MW

Number of units:

01

Annual Output:

3.9 billion kWh

The plant uses coal in pulverized combustion boiler to achieve high efficiency, stability, safety and requirements for environmental protection due to state-of-the-art equipment. Essentially the plant operates at base load during dry season and intermediate load in wet season.

After finishing the plant will be connected to national grid at 500kV voltage to contribute a part in power supply for the Southern region from 2018 and help to reduce grid dependency to hydropower, especially in dry seasons and dry years.

2. Schedule

  • Ground breaking ceremony: 13 December 2014
  • Finish of boiler drum lifting for Unit No.1: 20 January 2015
  • Finish of boiler drum lifting for Unit No.2: 07 April 2015
  • Issue of Provisional Acceptance Certificate for Unit No.1: October 2016
  • Synchronizing Unit No.1 to national grid: 15 September 2016
  • Issue of Provisional Acceptance Certificate for Unit No.2: February 2017


  • 29/12/2016 10:21
  • 8076