Mission inspecting construction site of Ialy Hydropower Plant Extension project with participation of EVN’s professional departments and contractors involved in construction of project.
Mr. Pham Hong Phuong – EVN’s Vice President (2nd row from the left) discussing with Power Project Management Board No.2 and contractors about project progress.
Mission inspecting water intake site. In first quarter of 2023, regarding construction of water intake, installation of 14T tower crane has been completed, concrete bottom slab completed to a height of 474m, reaching 100% of plan, meeting project construction schedule.
Up to now, water tunneling, penstock digging and reinforcement, lower surge tank concreting, etc. have been completed. In the photo, mission inspecting water tunnel.
Currently, on construction site of Ialy Hydropower Plant Extension project, there are nearly 700 employees of Power Project Management Board No.2 and contractors. The whole construction workforce has been accelerating project implementation, working continuously with 3 shifts, 4 teams to ensure project progress. In the photo: Construction area of Ialy Hydropower Plant Extension project