EVN leader inspects progress of key power grid projects in Quang Ninh

12:24, 17/11/2026

On the morning of November 17, Vietnam Electricity (EVN) Vice President Pham Hong Phuong and a delegation conducted on-site inspections and reviewed construction progress at two key power grid projects in Quang Ninh Province: the Cong Hoa 220kV Substation and its associated connection lines and outgoing 110kV feeders; and the Hai Ha – Mong Cai 220kV Transmission Line Project.


EVN Vice President Pham Hong Phuong (wearing striped shirt and safety helmet) and delegation inspect construction progress at Cong Hoa 220kV Substation and its associated connection lines and outgoing 110kV feeders. The project, located in Hai Hoa Commune, Quang Ninh Province, is invested by Northern Power Corporation (EVNNPC).

The Cong Hoa 220kV Substation is designed to accommodate two 220kV–250MVA transformers, with one transformer to be installed in the current phase. Pictured: EVN Vice President Pham Hong Phuong discusses project implementation with representatives of EVNNPC, the project investor, at construction site.

Construction of the project commenced in late May 2026. According to observations at the site, site grading works for the Cong Hoa 220kV Substation have been substantially completed.

Sites have also been handed over for all four tower foundation locations of the outgoing 110kV feeders from the Cong Hoa 220kV Substation. Pictured: Workers carry out foundation construction for outgoing 110kV feeders.

EVN Vice President Pham Hong Phuong and delegation inspect tower location VT68 of Hai Ha – Mong Cai 220kV Transmission Line. The project, invested by National Power Transmission Corporation (EVNNPT), has total length of approximately 23.7km and commenced construction on October 31, 2026.

According to the project investor's report, sites have been handed over for 54 out of 71 tower foundation locations. At location VT68, the contractor is carrying out site grading in preparation for foundation excavation.

* Note: The inspection program for key power grid projects in Quang Ninh Province is scheduled for November 17–18. Further updates will be provided on evn.com.vn.