Mr. Nguyen Tai Anh – EVN’s Vice President (front row, left) inspecting construction site of Quang Trach 1 Thermal Power Plant project. Plant includes 2 coal-fired units, capacity 2x701.5MW

Mr. Nguyen Tai Anh – EVN’s Vice President listening to representatives of Power Project Management Board No. 2 (EVNPMB2) and contractor's report on construction progress of project. Up to now, overall progress of project has reached 96.86%.

EVN leaders and working group inspecting coal import wharf area. Up to now, coal conveyor system has reached over 95% of its installed volume, expected to be tested on a single motor from November 30, 2025.

Mr. Nguyen Tai Anh – EVN’s Vice President acknowledging efforts of EVNPMB2, contractors, and consultants in maintaining construction progress, ensuring quality and safety in adverse weather conditions. Units striving to complete goal of connecting Unit 1 to grid as planned.

Panorama of Quang Trach Thermal Power Center