Mr. Nguyen Tai Anh - Vice President of EVN (top row, left) inspecting construction site of Quang Trach 1 Thermal Power Plant project.

EVN’s Vice President Nguyen Tai Anh listening to reports from representatives of Power Project Management Board No. 2 (EVNPMB2) and contractor on project’s construction progress. To date, Quang Trach I Thermal Power Plant project has achieved an overall progress of over 97.2%, with many key technical milestones already completed.

Coal Ship Unloader (CSU) system and conveyor belts BC01 – BC02 have undergone single-unit testing and are ready for combined operation.

During his site inspection, EVN’s Vice President Nguyen Tai Anh acknowledges efforts of EVNPMB2, contractors, and consulting unit in maintaining construction progress, ensuring quality and safety under adverse weather conditions.

Overview of Quang Trach Thermal Power Center project area