The last 'lego piece' of Duyen Hai Power Center

Duyen Hai 2 Thermal Power Plant is being urgently finished as per schedule by the project investor and related units, including Power Construction Consultant Joint Stock Company 2 (PECC 2) to complete the last "lego piece" of DUYENHai Power Center (Tra Vinh province).

Duyen Hai 2. Thermal Power Plant:

- Location: Mu U hamlet, Dan Thanh commune, Duyen Hai district, Tra Vinh province.

- As the last plant in the planning of Duyen Hai Power Center.

- Scale: 2x660MW, using traditional condensing turbine technology.

Duyen Hai 2 Thermal Power Plant Project was commenced in August 2016, by JanakuasaVietnam Co., Ltd., (belonging to Janakuasa Co., Ltd., Malaysia) as the investor and PECC 2 as the management consulting unit of the project.

Up to now, the implementation progress has reached over 96% of the total quantity of the project with many important items completed such as: the 500kV transmission line system connecting the plant to the 500kV Duyen Hai substation; main machine chamber items; system of supplying and processing coal and oil fuels; water treatment system; desulfurization system; ash storage system; fire protection system; office building, and so on.

Unit 1 of Duyen Hai 2 Thermal Power Plant has generated commercial power to the national grid from June 1, 2021.

On 14 April 2021 and 30 May 2021, units 1 and 2 of Duyen Hai 2 Thermal Power Plant, respectively, were successfully synchronized into the national power system.

By 1 June 2021, unit 1 had completed the testing stages and necessary procedures as prescribed, ensuring quality to start commercial operation date (COD), completed 1 month ahead of the schedule. It is expected that in July 2021, unit 2 and the whole plant will be completed and put into commercial operation.


  • 21/07/2021 02:07
  • evn.com.vn
  • 1723