The delegation of the Office of the National Steering Committee for Electricity Development conducted a field inspection of the site where there were problems with the land of the Nha Trang - Thap Cham 220kV transmission line project in Ninh Thuan province.
In Ninh Thuan province, the National Power Transmission Corporation (EVNNPT) is implementing four urgent power transmission projects.
Specifically, the Van Phong - Vinh Tan 500kV transmission line project crosses Ninh Thuan province with 132 foundation positions. To date, EVNNPT has paid and mobilized the landowners to hand over their land for the entire foundation position; EVNNPT has paid for 109/132 pole spans of the line corridor.
The 500kV transmission line project connecting the Thuan Nam 500kV substation to the Van Phong - Vinh Tan 500kV transmission line has been handed over 3/3 of the pole positions. Currently, the units are working on digging and casting foundations.
The Nha Trang - Thap Cham 220kV transmission line crossing Ninh Thuan province has 56 foundation positions. Up to now, the locality has paid for the handover of all pole spans.
For the Ninh Phuoc double circuit 220kV transmission line project - Thuan Nam 500kV substation, the locality paid and mobilized the landowners to hand over their land for 29/34 foundation positions and 21/34 pole spans of the line corridor.
Mr. Hoang Trong Hieu - Deputy Chief of Office of the National Steering Committee for Electricity Development speaking at the meeting
Mr. Hoang Trong Hieu - Deputy Chief of Office of the National Steering Committee for Electricity Development suggested the National Power Transmission Corporation closely in coordination with local authorities to fully implement legal procedures in the work of compensation for site clearance, and at the same time require contractors to prepare enough human resources so that when the locality organizes enforcement, the construction will be carried out immediately with the shortest time.