09:24, 16/12/2016
Investor:
EVN/EVNNPT
Project manager:
The Southern VietNam Power Projects Management Board
Project Consultant:
Power Construction JSC No.3
Total investment:
Investment sources:
Length (km):
2x75
Start:
2016
Finish (expected):
2018
09:26, 16/12/2016
09:25, 16/12/2016
09:23, 16/12/2016
Operational situation in October 2025; Objectives and tasks in November 2025
Completion of 220kV transmission line project to relieve capacity of Nhon Trach 3 Power Plant
EVN and UK Foreign, Commonwealth and Development Office exchange signed Memorandum of Understanding on cooperation in energy and green grid development
EVN supports people of Da Nang and Hue cities with VND 2 billion to overcome consequences of natural disasters
Reinforcement completion of Muong Te 220kV Substation to 750MVA
EVN submits two-component pricing model
Vietnam navigates regulatory hurdles in renewable energy push
Inauguration Ceremony of Lao Cai - Vinh Yen 500kV Transmission Line Project
EVN and Australia’s CSIRO share experiences on battery energy storage system (BESS) integration
Renewable energy investment is booming again in Vietnam