Ministry of Industry and Trade approves power generation price framework for solar power plants
16:10, 10/04/2025
The Ministry of Industry and Trade (MOIT) has just issued Decision No. 988/QD-BCT dated April 10, 2025, approving the power generation price framework applicable to solar power plants.
Accordingly, the 2025 power generation price framework to be applied to the type of solar power plant specified in Point a, Clause 2, Article 1 of Circular No. 09/2025/TT-BCT dated February 1, 2025, of the Minister of MOIT stipulating the dossier, order, procedures, methods for determining and approving the power generation price framework; stipulating the dossier, order, procedures for developing and approving the electricity import price framework.
In addition, the parameters of the electricity storage system (battery storage system) used to calculate the maximum price of the power generation price frame for the type of solar power plant with a battery storage system are as follows:
Capacity: Minimum 10% of the capacity of the solar power plant.
Time of storage/discharge: 2 hours.
Proportion of charging power output: 5% of the solar power plant's output
This Decision takes effect from the date of signing.