Ministry of Industry and Trade organizes conference on national power system operation and ensuring power supply in 2027-2028

12:06, 07/11/2026

On November 7th, at the Ministry of Industry and Trade (MOIT) headquarters, Minister Le Manh Hung chaired a conference on the operation of the national power system and ensuring power supply in 2027-2028.

Conference scene

2026: Ensuring sufficient power supply and optimizing performance amidst unprecedented challenges

According to reports from NSMO and other units at the Conference, in 2026, power supply will be simultaneously affected by several adverse factors. The crisis in the Middle East and the conflict in Ukraine disrupted supply chains, driving up primary energy prices significantly, greatly impacting Vietnam, a net importer of primary energy at approximately 44%. Specifically in April, May, and June, the system had to simultaneously deal with heatwaves, disruptions of fuel supply, LNG price fluctuations, and difficulties with imported coal.

Peak load exceeded the previous year's peak by 6.4%, with annual power demand increasing by over 10%, putting the greatest pressure on the North. Extreme weather patterns occurred, with several prolonged heatwaves in July, August, and September. The national average temperature in October was higher than the multi-year average, with the North experiencing a 2 to 3°C increase, reaching a record in the observation series since 1961.

The El Niño phenomenon, which began in the latter half of October, has reduced water levels in hydropower reservoirs to only about 80% of the multi-year average; the projected annual hydropower output is expected to be approximately 18.5 billion kWh lower than in 2025. Thermal power plants are under significant pressure due to the need to handle incidents and carry out repairs; bringing new base power sources into operation is very difficult and limited.

Mr. Nguyen Duc Cuong - Director of Electricity Department, delivering speech

In this context, under the direction of the Government and the Prime Minister, MOIT has directed the entire sector to implement comprehensive solutions to ensure sufficient power supply for socio-economic development and people's lives, not only ensuring sufficient power but also optimizing economic efficiency.

Meeting high load growth targets, total power production and imports for the entire system in 2026 are estimated at 356.2 billion kWh, an increase of 10.3% compared to that in 2025, approximately 6.2 billion kWh higher than the baseline scenario (8.5% increase). The system's peak capacity will reach 57,537MW in June 2026. Production in the North is expected to reach approximately 170.8 billion kWh, an increase of 11.9%; in the Central region, 33.7 billion kWh, an increase of 8.4%; and in the South, 151.8 billion kWh, an increase of 8.8%. In the fourth quarter of 2026 alone, the nationwide load is projected to increase by approximately 13%, in the North by about 14%, and in many provinces in the North and North Central regions by approximately 20%; however, the system is expected to meet demand.

Electricity is closely linked to economic growth. According to the Vietnam Electricity Group (EVN), in the first 10 months of 2026, commercial electricity sales increased by 9.84%, for the first time approaching the GDP growth rate; of which the trade and service sector increased by 13.8%, the management and residential consumption sector increased by 9.91%, and the industrial and construction sector increased by 8.84%.

The power supply and grid have been enhanced, proving their effectiveness. The development of rooftop solar power in the North has accelerated significantly. The Quang Trach I thermal power plant is undergoing trial operation and is expected to officially begin commercial operation at the end of 2026. Many key transmission grid projects supplying power to the North have been energized and are operating effectively.

Mr. Nguyen Duc Ninh - General Director of NSMO, delivering speech

Minister Le Manh Hung highly appreciated the efforts of the units under the Ministry, the coordination of ministries, sectors, and localities; affirming that the results in 2026 are the contribution of the entire system, especially the enterprises: NSMO, EVN, the power corporations, Petrovietnam, Vinacomin, the Dong Bac Corporation, and related units. The biggest lesson in managing in 2026 is proactively identifying risks and dangers; controlling and building scenarios; and coordinating closely, uniformly, and synchronously in implementation. This is also a lesson that must continue to be implemented in 2027.

Proactively and decisively propose series of solutions and tasks regarding operation methods and ensuring power supply in 2027-2028

This is the fifth meeting on the operation of the power system in 2027 and 2028. As early as May 2026, the leaders of MOIT directed the Electricity Department and the National Power Grid Management Agency to calculate and assess the power supply capacity for the next two years.

The conference noted that the operation of the power system in 2027 will face many intertwined challenges, and 2028 will be even more difficult: Electricity demand will continue to increase by about 10% on top of the high levels of 2026, while base power sources have not yet come into operation due to the need for investment time; El Niño may last until around June 2027, leading to complex hydrological developments, requiring both energy security and the fulfillment of water needs for agricultural production and domestic use downstream; the global geopolitical situation remains unstable, potentially impacting the supply chain and prices of imported coal and LNG.

Minister of Industry and Trade Le Manh Hung delivering speech at conference.

Based on calculations of various scenarios, NSMO proposed eight groups of solutions and recommended that MOIT establish a Steering Committee for power supply in the industry for the period 2027-2028, with consideration extending to 2030.

Concluding the conference, Minister Le Manh Hung emphasized that, in all circumstances, it is necessary to ensure sufficient energy supply in general, and power in particular, to meet the needs of economic development and people's lives through specific and feasible solutions.

The Minister of MOIT assigned specific tasks:

Firstly, it is urgent to finalize the operating method for the national power system in 2027, taking into account 2028 and beyond. The National Power Grid Management Agency (NSMO), in coordination with the Electricity Department, will calculate all power source projects with a long-term vision; propose specific baseline scenarios, operational scenarios, and inspection scenarios for the peak dry season; clarify the power supply capacity for each phase, paying attention to data, demand forecasts, and load curves; calculate the availability of power sources and risks, including simultaneous and double failures, ensuring the stability and redundancy of the system. The application of digital twin technology should be accelerated and put into operation no later than the first quarter of 2027. Immediately after the operating method is approved, MOIT will issue a Directive on ensuring power supply in 2027-2028.

Secondly, proactively regulate and store water in hydropower reservoirs to serve the 2027 dry season. The National Hydropower Project Management Board (NSMO) and the Electricity Department, in coordination with specialized agencies of the Ministry of Agriculture and Environment (MOAE) and localities, will store water to the maximum extent until December 31, 2026, and continue to retain water until March 31, 2027; manage water resources synchronously, optimally, and economically for power generation; and coordinate with the Department of Industrial Safety and Environmental Engineering to develop a plan for downstream water exploitation and use, submitting it to the two Ministries for agreement before December 31, 2026. The Minister requested MOAE to urgently submit to the Prime Minister a proposal to adjust the reservoir operation procedures.

Thirdly, maintain the available capacity of power plants. Units coordinating with plant owners and investors should develop a comprehensive plan for operation, maintenance, and repair, minimizing the impact of repairs and environmental issues on electricity supply; prioritize thermal power plant repairs from January to April, limiting shutdowns during the peak dry season and at the end of the year; and tighten operational discipline to prevent any incidents caused by human error.

Fourthly, ensure sufficient fuel for power generation according to the NSMO scenario. The Department of Energy - Oil and Gas, in coordination with Petrovietnam, PV GAS, Vinacomin, Brigade 19, and other enterprises, will develop a schedule for supplying coal, gas, and oil in sync with the operating method; promptly finalize the mechanism for supplementing imported LNG; complete the connection of the Cai Mep LNG terminal with the Thi Vai LNG terminal to ensure early gas supply; and ensure sufficient reserve coal and oil stocks before the dry season.

Fifthly, focus on accelerating key power generation and grid projects. The Electricity Department will work with investors to review and expedite progress, ensuring the synchronization of power sources and grids, avoiding scattered and wasteful investments; accelerate the construction of 500kV substations to supply electricity to the North; and boost electricity imports.

Sixthly, urgently implement solutions to supplement peak power capacity. Develop battery energy storage systems (BESS) according to the defined scale and price framework; EVN, Petrovietnam, Vinacomin, and investors review and register the scale of investment in storage. People's Committees of provinces and cities coordinate with the electricity sector to promote rooftop solar power in industrial parks, large customers, and offices; implement the assignment of rooftop solar power development targets to localities.

Seventhly, tighten and strengthen electricity demand management. Effectively implement Directive No. 10/CT-TTg on electricity saving; implement load adjustments, striving to reduce peak power in the North by at least 3,000MW in 2027; promote the efficient use of economical electricity in production, business, and daily life, especially during peak hours.

Eighthly, ensure clear responsibilities and proper authority in implementation. Based on the responsibility matrix, define the specific roles of each agency and unit for performance review.

Regarding inter-sectoral coordination, the Minister requested that ministries and sectors, especially MOAE and the Ministry of Finance, closely coordinate with localities to implement the operational method for 2027 in a synchronized and effective manner, taking into account the period up to 2028.


Translator: Nguyễn Thị Lan Anh