According to the plan, the 500kV transmission line project connecting Nghi Son 2 thermal power plant to the national power system (2 lines, each with dual circuits) will be commissioned and put into operation in March 2021, to supply power for the trial run and capacity release of this plant.
Currently, the construction of line 2 of the project has been completed, and in the process of technical acceptance and ready for acceptance and energization; However, there is an obstacle for route 1 bracing, the problem of site clearance compensation, failing to meet the progress of acceptance in March 2021.
EVN Deputy General Director Pham Hong Phuong (front row, in the middle) chairing the meeting
Based on the actual situation, the National Power Transmission Corporation (EVNNPT), the Central Power Project Management Board (CPMB) and the consulting unit have developed a plan to power off the 500kV North-South to organize the connection and energizing and put into operation the 500kV grid connecting the Nghi Son 2 BOT power plant to the national power system via Line 2.
Under the direction of EVN's Deputy General Director, the Investor shall complete the construction for energizing the 500kV grid to connect line 2 before 27 March 2021 and line 1 in May 2021.