Focusing resources on implementing Hoa Binh Hydropower Plant Extension project

That was the request of Vietnam Electricity’s Vice President - Mr. Pham Hong Phuong at the meeting on reviewing the construction progress of Hoa Binh Hydropower Plant Extension project. The meeting took place on 4 March 2021 in Hanoi.

EVN’s Vice President Pham Hong Phuong chaired the meeting

To keep up with the project construction schedule in 2021, EVN's Vice President requested EVN's functional departments to drastically "step in", inspect and give directions to put the construction site into order. Power Project Management Board No.1 is requested to closely collaborate with the local authorities to complete the site clearance work in March 2021.

Quickly reporting on the situation at the project site, the PMB said that the entire apparatus of the Executing Board and the Supervisory Consulting Organization has been streamlined. The Joint Collaboration Board with the contractor consortium has been further strengthened such as the department of design of construction measures, safety management and environment department, expected to be completed in March 2021.

Regarding the personnel mobilization to the site in 2021, it is planned to mobilize 300 people to the project site in March 2021, and about 570 people at the peak time in July and August 2021.


  • 04/03/2021 04:10
  • evn.com.vn
  • 203