Can Tho City approves investment policy of O Mon III Thermal Power Plant Project

On August 4, 2022, Can Tho City People's Committee issued Decision No. 2447/QD-UBND approving Vietnam Electricity to invest in the O Mon III Thermal Power Plant project (in O Mon district, Can Tho city).

Perspective of O Mon Power Center (Can Tho)

O Mon III Thermal Power Plant Project covers an area of ​​about 8,342 hectares (area of main plant), is the land for energy works that has been leased by the People's Committee of Can Tho City to investors (paid annually) with a lease term from May 19, 2021 to February 24, 2050.

O Mon III Thermal Power Plant Project is scaled at a total investment capital of about VND 27,596 billion, equivalent to USD 1,190.5 million. The project's operation term is 31 years from the date of land lease decision (2021-2052). The location of project implementation is at O Mon Power Center, Phuoc Thoi Ward, O Mon District, Can Tho City.

The project construction is expected to be commenced in the first quarter of 2025 and generate power in the fourth quarter of 2027; start receiving gas in the fourth quarter of 2027; perform trial operation in the fourth quarter of 2027 and commercial power generation in the fourth quarter of 2027.

This is a combined cycle gas turbine thermo-power plant, with the scale in accordance with the approved industry planning to supply a stable power source for the Southern region in particular and the national power system in general, contributing to ensuring national energy security and safety of power supply, and together with thermal power plants in O Mon Power Center consuming all Block B gas.

Can%20Tho%20City%20approves%20investment%20policy%20of%20O%20Mon%20III%20Thermal%20Power%20Plant%20Project.pdf


  • 05/09/2022 03:21
  • evn.com.vn
  • 560