Chairman of EVN's Board of Directors Dang Hoang An works with EVNGENCO2

On November 8, in Can Tho, Chairman of EVN’s Board of Directors Dang Hoang An worked with Power Generation Corporation 2 (EVNGENCO2) on the production and business situation -construction investment - finance for 10 months of 2023 and implementation of the 2023 plan.

The representatives of Power Generation Corporation 2 attended the working session, including Mr. Tran Phu Thai - Chairman of Board of Directors, Mr. Truong Hoang Vu - Member of the Board of Directors cum General Director.

Chairman of EVN's Board of Directors Dang Hoang An giving instructions at the working session

Reporting at the meeting, Mr. Truong Hoang Vu - General Director of EVNGENCO2 said that EVNGENCO2 and its member units have basically completed the planned tasks assigned by EVN for the first 10 months of 2023 and other related tasks.

Specifically, the cumulative power output produced in 10 months of EVNGENCO2 reached 12.9 billion kWh, reaching 80.61% of the year plan; The total estimated output of the entire corporation in 2023 is 16 billion kWh. EVNGENCO2 also has achieved economic and technical targets. Major repair work of plants was basically completed on time and ahead of schedule compared to the registered plan. The implementation of training, employment and recruitment plan targets and labour productivity have basically met the scheduled plan.

Mr. Tran Phu Thai - Chairman of the Board of Directors of EVNGENCO2 making speech

Chairman of EVN's Board of Directors Dang Hoang An requested EVNGENCO2 to determine that good management of power plants and ensuring continuous, reliable operation with few incidents is the most important target. Coal thermal power units need to ensure fuel source and coal quality for electricity production and accelerate the progress of upgrading and renovation projects to meet environmental standards.


  • 08/11/2023 08:29
  • Evn.com.vn
  • 230