EPS engineers performing an overhaul of a main cooling circulation pump
The project was completed after 33 days of implementation, including 960 work items. More than 400 employees were mobilized mainly from EPS repair workshops at Vinh Tan (Binh Thuan)and Phu My (Ba Ria-Vung Tau) Power Centers.
Key items such as maintenance and repair of main turbine shaft bearings, boiler feed pump turbines (BFPTs), circulation pumps, seawater FGD (Flue Gas Desulfurization), etc., are all advanced equipment requiring high technical repair technologies, meeting strict standards specified by the manufacturer.
Ensuring safety, progress and quality of work, and quickly putting the unit into operation had contributed to ensuring the performance of the dual tasks of the Vietnam Electricity, meeting power supply requirements for disease prevention and control and maintaining the national energy security.
Vinh Tan 4 Thermal Power Plant under Vietnam Electricity (EVN), which includes three units with a total capacity of 1,800MW and generates an annual power output of about 12 billion kWh, plays an important role in the national power system. Since the plant went into operation in 2018, EPS's repair and maintenance team has always stood by the plant to successfully complete the power generating task, especially in the dry season months, to meet the power demand for socio-economic development in the Southern provinces.