Handing over Sesan 4 Solar Power Plant to Sesan Hydropower Development Company

On 4 January 2022, in Kon Tum, Vietnam Electricity (EVN) held a ceremony to hand over Se San 4 Solar Power Plant Project to Se San Hydropower Development Company for operational management.

Se San 4 Solar Power Plant Project with a capacity of 49MWp is invested by EVN, and managed by Power Project Management Board 2.

The project will be implemented from 20 December 2019, generated commercial power on 22 November 2020 and completed by EVN Acceptance Council and put into use from 30 November 2020. Currently, the EPC contractor has completed 1 year of operation according to the terms and conditions of the contract.

The operation of power generation in the first year under the contract by Sesan Hydropower Development Company under the contract shows that the average number of converted operating hours in a day is 3.73 hours/day, the generated power output is 71.26 million kWh. 

EVN’s Deputy General Director Nguyen Tai Anh (6th from left) handed over the key to Se San 4 Solar Power Plant Project to leaders of Se San Hydropower Development Company

Sesan 4 Solar Power Plant:

- Construction site: Ia Toi commune, Ia H'Drai district, Kon Tum province;

- Total investment: VND 937.1 billion;

- Average power output: 72.4 million kWh/year.

 


  • 05/01/2022 09:02
  • evn.com.vn
  • 813