The Bac Giang-Lang Son 220kV power line project has a construction scale of two circuits (currently deploying one overhead circuit), with a total length of 101.6 km, from the Bac Giang 220kV substation (existing) to the Lang Son 220kV substation (new construction), including 236 foundation positions and 80 dead ends.
Up to now, the project has been handed over the land for 233/236 foundation positions. three positions that have not been handed over in Huu Lung and Chi Lang districts (Lang Son province). The section of the corridor has handed over 46/80 deadends. According to the plan, localities commit to handing over the remaining land in October 2022.
In terms of construction progress, up to now, the project has completely cast the foundation with 231/236 positions, completely erected poles at 222/236 positions, and completely pulled the conductors for 25/80 anchorages (equivalent to 23.2 km/101.4 km).
Mr. Nguyen Duc Tuyen – Director of CPMB chaired the meeting on 22 September 2022
Currently, the work of pulling the conductors and erecting poles of the construction unit is slower than the planned schedule. At the site inspection on 22 September 2022, Mr. Nguyen Duc Tuyen - Director of CPMB, required the construction contractor to increase manpower and equipment, accelerating progress to complete the project by the end of 2022.