Two projects of Phuoc Thai 2 and Phuoc Thai 3 solar power plants are invested by Vietnam Electricity; Power Project Management Board No.2 manages the project implementation. Both projects are built in Phuoc Thai commune, Ninh Phuoc district, Ninh Thuan province.
Signing ceremony between representatives of Power Project Management Board No.2 and the consortium of contractors implementing EPC packages of Phuoc Thai 2 and Phuoc Thai 3 Solar Power Projects
In which, the solar power plants use monocrystalline silicon photovoltaic panels, direct grid connection, no storage, string inverters, the installed capacity of Phuoc Thai 2 solar power project is 100MWp and of Phuoc Thai 3 is 50MWp. Both power plants are connected to the national power system via Vinh Tan - Thap Cham 220kV transmission line.
The contractor selection results have been approved by Vietnam Electricity at Decision No. 1447/QD-EVN dated 29 October 2021; Decision No. 1677/QD-EVN dated 3 December 2021 and the winning bidder is the consortium of Risen Energy Co., Ltd. (Hong Kong, China) and Tasco Joint Stock Company (Vietnam).
Representative of Risen Energy Co., Ltd (Hong Kong, China) attended the online signing ceremony
The consortium of contractors is committed to making every effort to put the projects into operation on schedule, ensure quality and safety, and meet the requirements of the project investor - Vietnam Electricity.
According to the plan, the two projects will be completed and put into operation in the third quarter of 2022. Upon completion, they will add an annual electricity output of over 247 million kWh to the national power system, contributing to the local socio-economic development and the national industrialization and modernization process.
Two projects of Phuoc Thai 2 and Phuoc Thai 3 solar power plants:
- Project investor: Vietnam Electricity;
- Representative of the project investor: Power Project Management Board No.2;
- Phuoc Thai 2 Solar Power Plant with a capacity of 100 MWp, annual electricity output of about 166 million kWh;
- Phuoc Thai 3 Solar Power Plant with a capacity of 50 MWp, annual electricity output of about 80.8 million kWh;
- Commercial operation date: 143 days from the effective date of the Contract.
- Acceptance and issue of provisional acceptance certificate (PAC): 177 days from the effective date of the Contract.
|