Complete the 2023 plan
2023 is the first year that the self-consumption electricity rate reaches less than 10%, more economical than the Group's assigned plan.
Mr. Ngo Son Hai - Member of the Party Standing Committee, Vice president of EVN directing the conference
The company identifies environmental protection as a central work throughout production activities. Over the past time, the Company has always ensured strict and full compliance with environmental regulations. TBTPC has consumed 100% of the generated ash and slag.
Mr. Ta Trung Kien – Company’s Party Committee Secretary, Director answering the recommendations and questions of workers within the framework of the 2024 Labor Conference program
Focus on operating power units safely, reliably, and effectively
In 2023, the Company reached the cumulative production milestone of 20 billion kWh, contributing to the socio-economic development of Thai Binh province and the Northern region.
State Controller (CMSC) at EVN Bui Dinh Thanh authorized to award the Certificate of Merit from the Committee for Management of State Capital at Enterprises and the Title of Committee-level Emulation Fighter to Mr. Tran Duc Thuat - an outstanding staff of TBTPC.
Vice president of EVN Ngo Son Hai awarding EVN Certificates of Merit to outstanding collectives in 2023
In 2024, Thai Binh Thermal Power Company aims to complete the production, business, and investment plan assigned by EVN, ensuring the readiness of furnaces, machines, and fuel to meet the mobilization needs of the power system with the target of power output in 2024 at 3,861 million kWh.
Vice Chairman of Vietnam Electricity Trade Union Uong Quang Huy granting awards to outstanding collectives
Some other indicators of TBTPC in 2024:
- Self-consumed electricity for the entire plant ≤ 11.00%.
- Heat loss rate: ≤ 10,616 kJ/kWh.
- Plant availability coefficient ≥ 84.52%.
- Machine downtime rate: ≤ 2.74%.
- Planned machinery stoppage rate: ≤ 17.74%.
- Response coefficient: ≥ 94.04%
|