EVN and lenders discuss measures to accelerate loan disbursement for Bac Ai Pumped-Storage Hydropower Project

17:13, 10/11/2026

On the afternoon of 10 November in Hanoi, Vietnam Electricity (EVN) held a meeting with a delegation of lenders financing the Bac Ai Pumped-Storage Hydropower Project to address outstanding issues and accelerate the signing of loan agreements and disbursement of funds for the project.

Representing EVN were Vice Presidents Nguyen Dinh Phuoc and Pham Hong Phuong, together with representatives of the Group's relevant departments and Power Project Management Board 3 (EVNPMB3).

The lenders' delegation included representatives from the French Development Agency (AFD), Proparco, a development finance institution within the AFD Group, CDP, a global environmental non-profit organization, KfW Development Bank, the Japan International Cooperation Agency (JICA), the European Investment Bank (EIB), and the Delegation of the European Union (EU).

Lenders' delegation (left) meets with EVN on afternoon of 10 November to discuss Bac Ai Pumped-Storage Hydropower Project.

The meeting was divided into two sessions. The first, chaired by EVN Vice President Nguyen Dinh Phuoc, focused on financial matters and loan disbursement conditions. The second, chaired by EVN Vice President Pham Hong Phuong, sought to align priorities for the delegation's working programme, particularly the scheduled site visit and meeting with the Khanh Hoa Provincial People's Committee on 11–12 November.

During the first session, both sides discussed measures to expedite the signing of loan agreements and the disbursement of financing for the Bac Ai Pumped-Storage Hydropower Project.

Particular attention was given to environmental and social requirements, including the biodiversity action plan and environmental management and monitoring arrangements, to ensure compliance with the conditions precedent to the first loan disbursement.

EVN Vice President Nguyen Dinh Phuoc (second from right) speaks at meeting.

Vice President Nguyen Dinh Phuoc proposed that the lenders which have already signed loan agreements with EVN, namely AFD, Proparco, and CDP, consider allowing their respective loans to be disbursed independently. This would facilitate the timely reimbursement and settlement of project expenditures that EVN has pre-financed using its own resources.

He also expressed his expectation that the lenders' working programme would enable participating financial institutions to gain an objective and accurate assessment of the project's implementation progress, thereby helping accelerate the signing of the remaining loan agreements and subsequent disbursements.

During the second session, Vice President Pham Hong Phuong provided an update on the project's implementation. Overall, progress across the main construction components has largely remained in line with the established schedule.

The most significant challenge currently concerns complex geological conditions encountered in the VH3A construction and operation tunnel. The contractor has completed excavation and reinforcement works through the geological fault zone and is now concentrating resources on recovering lost time.

For the remainder of 2026, the construction consortium will deploy seven simultaneous work fronts, focusing on tunnel excavation, excavation of the powerhouse foundation pit, and completion of the VH1, VH2, and VH3A construction and operation access routes.

The project aims to secure access to the required construction area and establish the necessary conditions for work on the upper reservoir by approximately February 2027.

Regarding biodiversity offsets, compensatory afforestation, forest environmental service payments, social policies, compensation, and resettlement assistance, EVN has been working closely with the Khanh Hoa Provincial People's Committee to develop specific implementation plans in accordance with Vietnamese law.

EVN has also recently signed the contract for the electromechanical equipment supply package with the consortium of Voith Hydro Shanghai and Powerchina Zhongnan. Together with the ongoing civil works package, these two major contracts are critical to the overall implementation schedule of the project.

EVN Vice President Pham Hong Phuong (right) provides update on project's implementation progress.

Vice President Pham Hong Phuong emphasized that timely loan disbursement is essential to achieving the project's target of commissioning its first generating unit in December 2029.

He expressed EVN's expectation that the working programme would help both sides resolve outstanding issues and agree on a clear roadmap for completing the remaining tasks, particularly the conditions precedent to the initial disbursement.

Representatives at signing ceremony for electromechanical equipment supply contract for Bac Ai Pumped-Storage Hydropower Project on 26 October 2026.

The lenders' delegation is conducting its working programme from 9 to 13 November to monitor and assess project implementation, complete outstanding environmental and social, technical, financial, and legal due diligence, and review progress towards satisfying the conditions precedent to the first disbursement under the signed loan agreements.

The programme is also intended to support participating financial institutions in completing their respective loan approval processes.

The Bac Ai Pumped-Storage Hydropower Project, located in Bac Ai Tay Commune, Khanh Hoa Province, has a total estimated investment of approximately VND 21.101 trillion and an installed capacity of 1,200MW, comprising four generating units of 300MW each.

As a key power generation project under National Power Development Plan VIII (PDP VIII), the facility is designed to store energy and generate electricity during peak demand periods, contributing to the stability of Vietnam's national power system.

The project targets commissioning its first generating unit in December 2029, with the remaining units scheduled to enter operation in 2030.