Thac Mo Hydropower Plant achieves 2026 generation target 40 days ahead of schedule
17:30, 23/11/2026
As of 5:00 on 21 November, Thac Mo Hydropower Plant had generated 693.02 million kWh, fulfilling its 2026 generation target assigned by the Ministry of Industry and Trade 40 days ahead of schedule.
This figure accounts for about 90.9% of Thac Mo Hydropower Joint Stock Company's total generation target (762.38 million kWh). The remainder comes from the Thac Mo Expansion Hydropower Plant and the Thac Mo Solar Power Plant.

Reservoir of Thac Mo Hydropower Plant and Thac Mo Expansion Hydropower Plant
Since the beginning of the year, Thac Mo Hydropower Plant (TMP) has proactively developed its production plan and closely followed its operating schedule. The company focused on improving the availability of its generating units, managing techno-economic indicators, enhancing the effectiveness of equipment maintenance and repair, and accelerating the application of digital technologies in management and operation.
Faced with unusual developments in the hydrological situation in 2026, TMP proactively monitored rainfall and water inflows to the reservoir, updated and calculated operating plans for its generating units, and regulated the reservoir appropriately. The company also strengthened coordination and information exchange with competent authorities and relevant units to respond proactively to emerging situations and ensure the safety of the facilities and the downstream area.
For the remainder of 2026, TMP will continue to ensure the safe and stable operation of its generating units and improve power generation efficiency, while making efficient use of water resources, meeting downstream water demand, and preparing to implement its 2027 generation plan.
Translator: Hải Yến