Duyen Hai 3 Thermal Power Plant Extension Project completed boiler hydrostatic test 

On July 31, 2017, at Duyen Hai 3 Thermal Power Plant Extension Project site, Contractors together with the Project Owner and the Construction Supervision Consultant have completed boiler hydrostatic test for the Plant. This was the first milestone in the 180 consecutive day campaign from July 15, 2017 to January 15, 2018 towards the first coal combustion for the Project.

The test had been conducted by LILAMA 18 (the Contractor for construction and installation) under supervision and inspection of the Project Owner’s representative – Power Generation Corporation 1, the main Contractor Sumitomo and the Construction Supervision Consultant. 

Upon completion of the boiler hydrostatic test, contractors would continue examining and finalizing project items, at the same time mobilize their on-site workforces at the maximum level to complete the project’s milestones on schedule as committed to the Project Owner.

Duyen Hai 3 Thermal Power Plant Extension Project under Duyen Hai Thermal Power Complex located in Dan Thanh commune, Duyen Hai district, Tra Vinh province includes a 600 MW power unit. It is scheduled that the Plant will be put into operation by the year 2018, supplementing a power generation source to Southern provinces and cities, with the annual average electricity generation output of approximately 3.9 billion kWh. 


  • 01/08/2017 01:51
  • evn.com.vn
  • 2232