EVN assigned to be project investor of the Dung Quat I, Dung Quat III Mixed gas turbine power plants, and Dung Quat I, II and shared infrastructures project of Dung Quat I, II, III Mixed gas turbine power plants mining the Green Whale gas field by the Government.
Up to November of 2017, EVN have selected consultants for preparing of pre-feasibility and feasibility reports ofDung Quat I, Dung Quat III Mixed gas turbine power plants in accordance with current law regulations.
It is expected that EVN will have completely selected the consultants within February 2018 and the project shall be employed in March 2018. Of which, for the Shared infrastructure project for Dung Quat I, II and III mixed gas turbine power plants is planned to be approved in early of July 2018, the compensation and ground clearance will be completed in July 2019 and the construction of shared infrastructure will be completed in February 2020.