The meeting was also attended by EVN’s General Director Nguyen Anh Tuan, Member of EVN’s Board of Directors Nguyen Duc Cuong, EVN’s Vice President Pham Hong Phuong, leaders of EVN's specialized departments, leaders of the National Power Transmission Corporation, construction contractors, designers, consultants, and equipment suppliers for the project, and so on.
The 500kV, circuit 3, transmission line project, from Quang Trach to Pho Noi, includes 4 component projects: Quang Trach - Quynh Luu, Quynh Luu - Thanh Hoa, Thanh Hoa - Nam Dinh I Thermal Power Plant, Nam Dinh I - Pho Noi Thermal Power Plant; with a total length of about 519km, passing through 9 provinces (including 4 towns and 39 districts). With the drastic direction by the Prime Minister and the drastic participation by local authorities, up to now, on the entire route, 1,118/1,180 (reaching 95%) post foundation positions and 179/502 (reaching 36%) anchorage spaces have been handed over.
Currently, contractors have completed foundation casting for 87 positions; temporary road construction and foundation construction are underway at 752 locations; completed installation of 1 steel post and 6 posts are being installed.
Chairman of EVN's Board of Directors Dang Hoang An chairing the meeting
At the meeting, the contractors reported the status of implementing the bidding packages, pledging to make maximum efforts and concentrate resources to complete the work items according to the schedule requested by the investor.
Speaking at the meeting, Chairman Dang Hoang An emphasized that this is a key, urgent energy project with very important significance to strengthen the capacity of the 500kV transmission grid from the North to the Central, contributing to ensuring power supply for the North. The project received the attention and drastic direction of the Government, the Prime Minister, and the participation of the entire political system.
According to the Prime Minister's direction, the entire line must be energized in June 2024. The Chairman of EVN's Board of Directors requested contractors to prioritize, devote all resources to the project, and increase human resources and equipment to urgently deploy immediately at locations that have been handed over. Consulting and design units need to further promote their roles and speed up the construction progress of work items. Contractors supplying materials and equipment such as steel poles, conductors, insulated accessories, fiber optic cables, etc., need to speed up production progress, ensuring quality and progress as committed. EVN’s leaders require contractors to jointly make greater efforts and determination to work with the investor to complete the project following the Prime Minister's direction.
Construction work of component projects of the project of 500kV line, circuit 3, from Quang Trach to Pho Noi, as of February 20, 2024:
* Nam Dinh I - Thanh Hoa Thermal Power Plant: completed foundation casting for 78/180 positions, road construction, foundation excavation, and casting or pile pressing are underway simultaneously at 98/180 foundation positions.
* Nam Dinh I - Pho Noi Thermal Power Plant: completed foundation casting for 7/334 locations, road construction, foundation excavation, and casting are underway simultaneously at 234/334 locations.
* Quynh Luu - Thanh Hoa: completed foundation casting for 1/203 positions, road construction, foundation excavation, and casting are underway simultaneously at 135/203 positions.
* Quang Trach - Quynh Luu: completed foundation casting for 1/463 locations, road construction, foundation excavation, and casting are underway simultaneously at 285/463 locations.
|