Chairman of EVN's Board of Directors Dang Hoang An inspects steel pole supply for circuit-3 500kV transmission line project

On 10 February 2024 (the first day of the Giap Thin Lunar New Year), in Hung Yen, Chairman of EVN's Board of Directors Dang Hoang An and the delegation inspected the steel pole supply for Quang Trach–Pho Noi circuit-3 500kV transmission line project of contractors.

Participating in the delegation was Mr. Nguyen Duc Cuong - a member of the Board of Directors of EVN, Mr. Nguyen Tuan Tung - Chairman of the Member Board of the National Power Transmission Corporation (EVNNPT), Mr. Pham Le Phu - EVNNPT President and CEO, and Mr. Nguyen Ngoc Tan – Vice President of EVNNPT.

According to EVNNPT's assessment, the capacity of the synchronous steel pole production line of Thanh Long contractor and joint venture contractors basically meets the volume that the contractor undertakes in the projects.

Chairman of EVN's Board of Directors Dang Hoang An (front row, second from right) and delegation inspecting steel supply of Viet Vuong Joint Stock Company 

At the inspection, representatives of the contractors said: Clearly determining that this is an important project, the unit has developed a detailed plan to ensure the steel pole supply is on schedule following the investor's request.

Delegation listening to contractor report on progress of steel pole production

Chairman of EVN's Board of Directors Dang Hoang An giving gifts to encourage workers of Viet Vuong Joint Stock Company for production during Tet

At the inspection, Chairman of EVN's Board of Directors Dang Hoang An acknowledged and appreciated the contractor for mobilizing large human resources to construct throughout the Tet holiday, joining forces with the power industry to ensure the progress of this urgent project; At the same time, he recommends the contractor to try and make more efforts because this is a project that receives close attention and direction from the Prime Minister. If the contractor delays the steel supply schedule, affecting the progress of the project, they will be responsible for the contract. 

Workers of Thanh Long Group Joint Stock Company performing production on first day of Lunar New Year

Chairman of EVN's Board of Directors Dang Hoang An also requested EVNNPT, the Northern Power Project Management Board, and The Central Power Project Management Board to regularly urge the timely progress of steel pole production and propose many effective solutions to shorten procedures to bring steel poles to the construction site as quickly as possible. During the implementation process, if there are any problems, they need to be handled directly at the site so that the problems can be immediately resolved to meet the project progress targets.