EVNHCMC: The time to handle new connections via medium voltage substations is only 3.19 days

According to Ho Chi Minh City Power Corporation (EVNHCMC), since the beginning of the year, the Corporation has supplied electricity to 287 customers who have applied for new connections via medium-voltage grids, with an average processing time of 3.19 days.

In which, for 160 substations invested by the power sector at their own cost, the average number of processing days of the power sector is 4.05 days, that of the state management agencies is 1.36 days. As for 127 substations invested by customers, the average number of processing days in the power sector is only 2.37 days.

Customers in Ho Chi Minh City can easily register for new connections through customer care channels of the power sector

Over the years, EVNHCMC has improved their process of new connection delivery, i.e via stringing low voltage lines if load demand is ≤ 160 kVA or investing in a new dedicated substation if the demand is > 160 kVA. Accordingly, EVNHCMC will take the initiative to implement and bear all costs (except for electricity customers in the real estate business) and the only action that needs to be taken by the customer is to register for a new connection.


  • 22/09/2022 04:43
  • evn.com.vn
  • 169