Energizing 220kV connection line of Tan Uyen 500kV substation project and connection

At 19:36 on 24 December 2020, in Binh Duong province, the Southern Viet Nam Power Project Management Board (SPMB) coordinated with the relevant units to successfully energize the 276 Tan Uyen - 272 Thu Duc and 279 Tan Uyen - 272 Long Binh lines under the Tan Uyen 500kV substation and connection.

The 220kV feeder and connection line under the Tan Uyen 500kV substation project and connection

The project scope of Tan Uyen 500kV substation and connection in the 2015 – 2020 period includes investment in construction and installation of 1 500/220/35kV-900MVA and 1 220/110/22kV-250MVA transformers; 220kV connection line includes 4 circuits (10.5km overhead line and 1.9km underground cable) to connect to the Long Binh - Thu Duc 110/220kV mixed line.

In the period up to 2025, installation of 2 500/220/35kV-900MVA and 3 220kV/110/22kV-250MVA transformers, reserving position for 3rd 500/220/35kV transformer installation (after 2025).
Once completed, the project will release the capacity of Vinh Tan and Van Phong Power Centers, enhance the power supply capacity to meet the economic development needs of Binh Duong, Ho Chi Minh City and surrounding areas.
The project is invested by the National Power Transmission Corporation (EVNNPT), managed by SPMB. Power Construction Consulting Joint Stock Company 3 is a design consultancy, supervision and construction unit. Power Transmission Company 4 takes over and manages the operation when the project is completed.


  • 26/12/2020 10:08
  • evn.com.vn
  • 303