Huong Khe unmanned 110 kV substation comes into operation (Ha Tinh province)

On May 31, 2017, the Northern Power Corporation successfully energized the Huong Khe 110 kV substation and transmission line project. This is the most state – of – the – art substation in Ha Tinh province which will operate in an unmanned mode.

Energizing to put Huong Khe 110 kV substation into operation. 

The Northern Power Corporation has delegated Huong Khe 110 kV substation and transmission line project to Ha Tinh Power Company to be the project owner with the total investment cost of more than VND 190 billion.

The project’s scale is composed of: Huong Khe 110 kV substation with one 25 MVA transformer and five 35 kV feeders, four 10 kV feeders, together with a 37.7 km long 110 kV transmission line having the connection point at the end point of Ha Tinh 171T500 feeder.

The project in operation will contribute to securing safe and reliable electricity supply to 22 communes in Huong Khe district and 12 communes in Vu Quang district; as well as assisting electricity supply to Ha Tinh city when required.


  • 01/06/2017 04:09
  • evn.com.vn
  • 549