In six months, EVN completed 57 110 – 500kV power grid projects

This is one of the construction investment accomplishments of Vietnam Electricity in the first 6 months of 2019.

Vinh Tan - Song May - Tan Uyen 500kV transmission line was energized on April 27, 2019

In particular, EVN completed one 500kV project (Vinh Tan - Song May - Tan Uyen transmission line); 10 220kV projects and 46 110kV ones.

In addition, EVN has commenced construction of three 220kV power grid projects and 69 110kV ones.

In the last 6 months of 2019, EVN will continue deploying synchronous solutions to speed up the progress of projects. Particularly, EVN will strive to complete Vung Ang - Doc Soi - Pleiku 2 500kV transmission line on schedule in the second quarter of 2020.

The urgent power grid projects to supply electricity for the South are also scheduled to complete in 2020 such as: Song May - Tan Uyen, Song Hau - Duc Hoa (phase 1), Long Phu - O Mon 500kV transmission lines; Dong Hoi - Dong Ha - Hue, Pleiku 2 - An Khe, Binh Long - Tay Ninh, Kien Binh - Phu Quoc 220kV lines circuit 2, etc.

In the last 6 months of 2019, EVN will complete key power projects to supply electricity for Hanoi and big loads such as: Thuong Tin - West Hanoi 500 kV transmission line, 220kV branch of Viet Tri 500kV Substation, Thanh Nghi, Luu Xa and Thuy Nguyen 220kV Substations, etc.

In addition, EVN will keep on reviewing and reporting to the Ministry of Industry and Trade so that they can submit to the Prime Minister for approving the addition of projects for evacuating power from renewable energy sources and for powering loads into master plans.