The project is owned by the National Power Transmission Corporation (EVNNPT), implemented by the Power Transmission Project Management Board on behalf of the project owner, and then it will be transferred to Power Transmission Company 3 for operation.
Power Transmission Project Management Board and representatives of relevant companies performing project groundbreaking ceremony.
The project includes the installation of 01 new AT2 transformer with the capacity of 220/110/22kV-250MVA; On the 220kV side, extending the busbar, installing a new compartment for the transformer AT2; On the 110kV side, extending the busbar, installing a new compartment for the transformer AT2.
The investment objective of the project is to ensure a long-term stable and reliable power supply for Binh Dinh province's loads in normal operating mode and n-1 incident mode, thereby promoting the socio-economic development of Binh Dinh province; ready to evacuate power from regional renewable energy sources to the national power system; reducing capacity loss in the transmission network, improving production and business efficiency in EVN.
The project is scheduled to be completed and energized in the third quarter of 2024 in accordance with EVNNPT's direction.