Chairman of EVN's Board of Directors Dang Hoang An inspects construction progress of Hoa Binh Hydropower Plant expansion project

On 23 November 2023, in Hoa Binh province, the Chairman of EVN's Board of Directors Dang Hoang An, and the delegation of Vietnam Electricity (EVN) inspected the construction site of the Hoa Binh Hydropower Plant expansion project.

Bui Phuong Nam - Director of EVNPMB1 (far right) reporting to delegation on construction progress

Reporting on the project construction status, Mr. Bui Phuong Nam - Director of Power Project Management Board 1 (EVNPMB1) said that EVNPMB1 had completed handing over 78.91 hectares of land eligible for construction to the construction contractor, ensuring the overall progress requirements of the project. Many construction items met the planned schedule. For the construction of the water intake, EVNPMB1 has completed digging the foundation hole and is eligible to pour concrete; handed over their land, and construction of vertical wells No.1 and No.2 are underway; reinforced anchor drilling, poured concrete to cover the mechanical roof. For the plant construction, EVNPMB1 ensures progress in completing the concrete pouring of plant structures...

Calculating the construction volume to date, several items have met and exceeded the 2023 plan: plant foundation hole excavation reached 115%, and discharge canal hole excavation excavation reached 100%...

Delegation inspecting construction of water intake area

Chairman of EVN's Board of Directors Dang Hoang An chairing meeting on construction site about project implementation situation

Chairing the meeting on the construction site, Chairman of EVN's Board of Directors Dang Hoang An emphasized the importance of the Hoa Binh Hydropower Plant expansion project. EVN leader also noted that construction site progress has been pushed higher in recent months.

The expanded Hoa Binh Hydropower Plant project is located on the right bank of the existing Hoa Binh Hydropower dam in Phuong Lam ward, Hoa Binh city, Hoa Binh province. The 480MW capacity project is invested by EVN. The project was started in January 2021 with the expected progress of generating power for Unit 1 and Unit 2 in June-July 2025. The project is invested and constructed to increase the peak capacity of the national power system, exploiting the maximum annual excess water discharge during the flood season of the existing Hoa Binh Hydropower Plant to generate electricity. The work improves the frequency regulation and frequency stability of the national power system, contributing to reducing operating costs of the national power system, while reducing the working intensity of existing generating units, thereby extending the life of the equipment and saving maintenance and repair costs.