The gas volume supplied to each power plant will be in line with the gas supply agreement signed between the power plant owner and the gas supplier in accordance with the 2024 power supply and national power system operation plan approved by the Ministry of Industry and Trade.
The Ministry of Industry and Trade requires Vietnam Oil and Gas Group and Vietnam Gas Corporation to coordinate closely with gas field owners, power plant owners, Vietnam Electricity, and the National Load Dispatch Center to utilize gas resources appropriately within the allowable technical conditions of the gas supply system, safely operating the power system and respecting relevant commercial constraints, ensuring national interests, effectively using the country's resources and harmonizing the interests of all parties.
At the same time, coordinating with Vietnam Electricity and the National Load Dispatch Center to review and update the gas mobilization plan/gas supply capacity for power generation on a quarterly basis and report to the Ministry of Industry and Trade.
Gas-fired power plant owners in coordination with the National Load Dispatch Center and gas suppliers develop monthly and quarterly gas supply plans in accordance with the power supply and power system operation plan in 2024 approved by the Ministry of Industry and Trade and the monthly national power system operation plan announced by the National Load Dispatch Center; to ensure that power plants operate stably, safely, efficiently and meet safety and environmental protection requirements according to regulations, etc.
See details of Decision 3112/QD-BCT here