Ninh Phuoc 220kV substation and its connections Project Phase 1 to be energized in June 2020

By the end of April 2020, the land area of Ninh Phuoc 220kV substation and its connection power lines had been handed over. Central Vietnam Power Projects Management Board (CPMB) was urging its contractors to use all measures available to energize the Project Phase 1 by June 2020.

 Contractors are deploying construction urgently at Ninh Phuoc 220kV substation and its connections project

“Ninh Phuoc 220kV substation (2x250MVA) and its connections” is a key and urgent project, intended to collect renewable energy generated in the area and deliver it to the national network.

By the end of April, 2020, the land area of the substation and that of the power lines to the substation were completely handed over. 9 out of 12 locations of the 220kV branch line had been handed over to the construction unit, while 3 locations had not been handed over yet because the landowners had not agreed with the compensation price. The CPMB had been continuously following close to the local authorities to mobilize the landowners to hand over their land before 15 May, 2020.

In construction of the substation, 81% workload of removal of the vegetation layer and earth addition have been completed; construction of the substation fences, oil collecting tank in case of breakdown, control house, fire protection water tanks, road extension, water supply and drainage systems, grounding system, etc., are under way.

Contractors undertook that construction equipment and materials would be provided on schedule, in which final equipment and materials would be supplied by the end of May 2020.

The CPMB required the construction units to concentrate their human resources, their equipment, and prepare their detailed schedule of work, follow the emulation committed with the CPMB.

The project is invested by EVNNPT, and managed and operated by the Central Project Management Board of Central Power Works (CPMB). The project was commenced on December 27, 2019, in Phuoc Huu commune, Ninh Phuoc district, Ninh Thuan province. The project has been selected by EVN's Party Committee to be affixed with a name board in celebration of the 13th National Congress of the Party.