Photo series: Expanded Ialy Hydropower Power Plant’s construction site in the early spring days

Right from the beginning of the Year of the Tiger 2022, the construction site of Expanded Ialy Hydropower Plant has worked with urgency to meet the goal of completing the project in 2024. The photos were taken by evn.com.vn on 10-11 February 2022.

 

Power Project Management Board 2 (investor representative) and the contractors discuss the construction plan of the project's items on the construction site.

 

Right from the beginning of the Tiger Lunar New Year, the working spirit on the construction site has been very busy

Tunneling construction of Expanded Ialy Hydropower Plant

 

The construction site works all night to meet the project progress

 

Contractors will execute 3 consecutive shifts to meet the set schedule

 

Overview of Expanded Ialy Hydropower Plant construction site

Ialy Hydropower Plant Expansion Project:

- Investor: Vietnam Electricity

- Representative of the investor to manage and operate the project: Power Project Management Board 2

- Construction site: Ya Tang commune, Sa Thay district, Kon Tum province and Ia Mo Nong and Ia Kreng communes, Ialy town, Chu Pah district, Gia Lai province;

- Installed capacity: 360MW

- Total investment: nearly VND 6,400 billion 

- The whole project completed: QIV/2024