Facing complicated weather conditions and difficulties in the power supply of the system in the first 6 months of 2023, Phu My Thermal Power Company promptly developed a plan to ensure power production, closely monitor the situation of gas supply, reserve DO oil according to the required norm, strengthen control over technical and operational management, and strive to surpass the assigned power output targets assigned by EVNGENCO3.

Power production of Phu My Thermal Power Company in the first 6 months of 2023 is 5,455 million kWh, reaching 116.06% of the plan assigned by the corporation. The estimated power production output in 2023 is 10,803 million kWh.

The company has planned and closely monitored the gas supply situation, and made a reserve of sufficient DO oil in accordance with the norm to take the initiative in the fuel source, checked the fuel supply equipment system of the units to get ready for meeting all operating modes, performed safe and optimal fuel conversion in association with the gas supply situation and the needs of the power system.

Overview of Phu My Thermal Power Company

At the same time, the company has implemented the Project to improve the reliability and operating efficiency of plants, promoted the movement of technical improvement initiatives, effectively utilized PMIS technical management software, electronic operation log, and applied RCM to major repairs, and improved the efficiency of regular repair work, etc.

Phu My Thermal Power is trying to emulate production to reach the cumulative power output milestone of 330 billion kWh estimated by the end of August 2023. Also, according to the plan in 2023, the company will carry out 5 major repair works for the units of the expanded Phu My 2.1 Power Plant.

Phu My Thermal Power Company gets ready to meet the mobilization of power system dispatching