EVNHCMC's leaders said that at present, the power supply for Thu Duc city reached 4,322 kWh/person/year, doubling the national average rate.
EVNHCMC will participate in building electricity planning of Thu Duc city, building a project of developing smart power systems in the area, with the goal of increasing the power supply output to over 8,000 kWh/person/year and the power quality at the highest standard.
Mr. Hoang Tung - Deputy Secretary of the City Party Committee, Chairman of Thu Duc City People's Committee (standing) speaking at the meeting. Photo: Chi Lan
It is expected that in the third quarter of 2021, the Corporation will complete and energize the Phuoc Long 110kV station (2x63MVA) in Phuoc Long B ward to improve reliability and ensure power supply to Thu Duc city. Also in 2021, EVNHCMC will start the construction of new substations: Linh Dong 110kV, 220/110kV Thu Thiem and 110kV Thu Thiem 1. In the period of 2022 - 2025, the Corporation will continue to implement 110kV substations: Thu Thiem 2, Thu Thiem 3, 110kV substation in the area of Phuoc Thien Park.
In the period of 2021-2025, EVNHCMC will also coordinate with telecom units to implement 27 projects to underground the power grid and telecommunication cables in Thu Duc city. At the same time, proposing with the People's Committee of Ho Chi Minh City to supplement the list and accelerate the progress of underground works in Thu Duc city.