Successfully energizes transformer T2 at Doan Hung 110kV substation (Phu Tho)

Phu Tho Power Company has just coordinated with the Power Development Project Management Board (Northern Power Corporation) to successfully accept and energize Transformer T2,  Doan Hung 110kV Substation, Doan Hung district, Phu Tho province.

Transformer T2, Doan Hung 110kV Substation

As for the development of the load, transformer T1 (Doan Hung 110kV Substation) with a capacity of 40MVA (energized in October 2016) has often carried high loads at peak times, affecting the power supply, increasing power loss.

In response to the power supply situation of the region, the Northern Power  Corporation assigned the Power Development Project Management Board to install Transformer T2 (capacity of 40MVA), feeder compartments and remote control cabinets with the capability of operation parallel with the existing transformer T1. The project meets the requirements of monitoring, metering, remote control, to be put into operation in the unmanned substation mode.

Safe operation of the project will contribute to ensuring power supply for Doan Hung district; at the same time creating a flexible method of power supply between neighboring areas. In addition, the project also contributes to reducing power loss, improving power supply reliability, ensuring N-1 criterion, meeting the needs of load development. Therefrom, it will create a favorable investment environment for businesses as well as the general socio-economic development of Phu Tho province in accordance with the Electricity Development Plan of Phu Tho province.


  • 02/04/2021 11:35
  • evn.com.vn
  • 466