Wind power plant 7A
In August 2021, a number of wind power plants with specific capacity have been accepted to be put into commercial operation (COD) as follows:
Name of wind power plant
|
Number of turbines being COD accepted
|
Total capacity being COD accepted
|
Hoa Binh 1 – phase 2
|
04
|
15.2MW
|
Ninh Thuan 5
|
05
|
21MW
|
7A
|
03
|
12.6MW
|
Thus, at the end of August 2021, there were 24 wind power plants with a total capacity of 963 MW being put into commercial operation. EVN will continue to update and inform about the progress of commercial operation recognition (COD) of wind power projects before October 31, 2021.