Complete first cable-pulling package of 500kV circuit 3 transmission line project

On June 8, 2024, bidding package No. 39 of the 500kV transmission line project of Nam Dinh I Thermal Power Plant (TPP) - Thanh Hoa is the first package of the entire Quang Trach - Pho Noi 500kV circuit-3 transmission line project to complete the cable pulling work, 7 days ahead of schedule as requested by the investor.

The project has a length of about 74.4km, passing through the provinces of Nam Dinh, Ninh Binh, and Thanh Hoa. The project has 180 locations of tower foundation and to date has basically completed the tower erection work and is organizing the work of cable pulling.

Package No. 39 under Nam Dinh I TPP- Thanh Hoa 500kV transmission line project successfully completes the cable-pulling work

Mr. Le The Hanh - Director of Phuong Hanh Co., Ltd. said that the construction unit of package No. 39 in Nga Son district (Thanh Hoa province) includes 16 foundation positions (from position 67-82A), 6km respectively. After completing the stringing of package No. 39, the entire construction force of this package will be mobilized to reinforce other tower positions of the construction company. The unit showed the highest determination to have each tower erection completed. The unit will immediately organize cable pulling and is determined to complete 6 bidding packages (corresponding to 94 tower positions) following the schedule as required by the investor.

Deputy General Director of EVNNPT - Luu Viet Tien said: The 500kV circuit 3 transmission line project, the section of Nam Dinh I TPP-Thanh Hoa had more favorable conditions when the Prime Minister approved the investment policy earlier and the construction was commenced nearly 3 months earlier than the remaining 3 sections of the entire 500kV circuit-3 transmission line. Along with that, the construction process has always received consensus and support from the local authorities of the 3 provinces where the project passes. With the current progress, the project will meet the progress target assigned by the Prime Minister, which is to reach the finish line in June 2024.

The completion of the first cable pulling package of the 500kV circuit-3 transmission line project is of important significance and is the motivation for other units to actively strive with the highest determination to complete the project on schedule.

Up to now, the project has completed the tower erection and is pulling cables 46/74 anchor intervals (reaching about 62%)