Completing energization of Nam Dinh 1 TPP - Pho Noi section of 500kV circuit 3 transmission line

At 17h30 on August 19, 2024, the National Power Transmission Corporation, the Northern Power Project Management Board (NPMB) in coordination with relevant units successfully energized 2 circuits of 500kV circuit 3 transmission line, Nam Dinh 1 TPP - Pho Noi section.

The completion and energization of the project Nam Dinh 1 TPP - Pho Noi 500kV transmission line on schedule as requested by the Prime Minister is a great impetus to complete acceptance of and put into operation the entire 500kV circuit 3 transmission line project in the coming days according to the direction of the Prime Minister.

The Nam Dinh 1 TPP - Pho Noi 500kV transmission line project is about 127km long, passing through the provinces of Nam Dinh, Thai Binh, Hai Duong, and Hung Yen, including 334 foundation positions, 144 right-of-way spans. The project has been constructed since January 18, 2024, and was approved by the Investor-level Acceptance Board to be energized on August 16, 2024.

Leaders of EVNNPT, NPMB, and related units witnessing energization moment of Nam Dinh 1 TPP - Pho Noi 500kV transmission line project

500kV circuit 3 transmission line, Nam Dinh I TPP - Pho Noi section, completed and energized on afternoon of August 19, 2024

After completion, the project will alleviate the load and avoid overloading of existing 500kV transmission lines, ensuring the N-1 criteria. The transmission line also helps to increase the transmission stability reserve on the North-Central interface, combined with the 500kV transmission line sections Quang Trach - Quynh Luu - Thanh Hoa - Nam Dinh 1, contributing to supplementing capacity from power sources in the North Central region to the load center in the North.

Nam Dinh I TPP - Pho Noi 500kV Transmission Line Project:

- Investor: National Power Transmission Corporation (under EVN);

- Investor representative: Northern Power Project Management Board;

- Design consultant: Joint venture of Power Engineering Consulting Joint Stock Company 2 and Power Engineering Consulting Joint Stock Company 4;

- Operation unit: Power Transmission Company 1;

- This is a special-class energy project, group A;

- Construction commencement: January 18, 2024;

- Energization: August 19, 2024.

 