The completion and energization of the project Nam Dinh 1 TPP - Pho Noi 500kV transmission line on schedule as requested by the Prime Minister is a great impetus to complete acceptance of and put into operation the entire 500kV circuit 3 transmission line project in the coming days according to the direction of the Prime Minister.
The Nam Dinh 1 TPP - Pho Noi 500kV transmission line project is about 127km long, passing through the provinces of Nam Dinh, Thai Binh, Hai Duong, and Hung Yen, including 334 foundation positions, 144 right-of-way spans. The project has been constructed since January 18, 2024, and was approved by the Investor-level Acceptance Board to be energized on August 16, 2024.
Leaders of EVNNPT, NPMB, and related units witnessing energization moment of Nam Dinh 1 TPP - Pho Noi 500kV transmission line project
500kV circuit 3 transmission line, Nam Dinh I TPP - Pho Noi section, completed and energized on afternoon of August 19, 2024
After completion, the project will alleviate the load and avoid overloading of existing 500kV transmission lines, ensuring the N-1 criteria. The transmission line also helps to increase the transmission stability reserve on the North-Central interface, combined with the 500kV transmission line sections Quang Trach - Quynh Luu - Thanh Hoa - Nam Dinh 1, contributing to supplementing capacity from power sources in the North Central region to the load center in the North.
Nam Dinh I TPP - Pho Noi 500kV Transmission Line Project:
- Investor: National Power Transmission Corporation (under EVN);
- Investor representative: Northern Power Project Management Board;
- Design consultant: Joint venture of Power Engineering Consulting Joint Stock Company 2 and Power Engineering Consulting Joint Stock Company 4;
- Operation unit: Power Transmission Company 1;
- This is a special-class energy project, group A;
- Construction commencement: January 18, 2024;
- Energization: August 19, 2024.
|