Completion of Quang Ninh 500kV Substation Reinforcement Project Phase 1

Recently, the Northern Vietnam Power Project Management Board (NPMB - under the National Power Transmission Corporation) has accepted and energized the AT2 500kV-600MVA transformer under Quang Ninh 500kV Substation Reinforcement Project.

AT2 500kV-600MVA transformer at Quang Ninh 500kV Substation

The reinforcement project of Quang Ninh 500kV substation includes replacing two 500kV-600MVA transformers. In this phase, a  450MVA transformer is replaced by a 600MVA transformer with some other items.

This is a special grade energy project, group B, with a total investment of more than VND287 billion. The project is invested by the National Power Transmission Corporation (EVNNPT). NPMB is assigned to manage the project implementation. The Power Transmission Company 1 takes over and manages and operates it after completing the energizing.

The energized AT2 500kV-600MVA transformer contributes to ensuring the transmission capacity of power plants in the Northeast region according to the requirements of power system operation; preventing overloading of Quang Ninh 500kV substation, meeting the needs of socio-economic development in Quang Ninh province and surrounding areas.